Title: First Amendment to the Local Agency Program Agreement with the Florida Department of Transportation for the 62nd Avenue sidewalk improvement project from 62nd Street North to east of 58th Street North.
Attachments: 1. First Amendment -Executed, 2. Original Agreement, 3. Project Location Map-Revised Limits
Related files: 17-586D, 19-1415A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

First Amendment to the Local Agency Program Agreement with the Florida Department of Transportation for the 62nd Avenue sidewalk improvement project from 62nd Street North to east of 58th Street North.

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of the First Amendment to the Local Agency Program Agreement with the Florida Department of Transportation for the 62nd Avenue Sidewalk Improvement Project from 62nd Street North (N) to east of 58th Street N.

FDOT FPN No. 438022 1 38 01, and County PID No. 003306A

Body

 

Strategic Plan:

Ensure Public Health, Safety, and Welfare
2.5 Enhance pedestrian and bicycle safety

Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs
4.5 Provide safe and effective transportation systems to support the efficient flow of motorists, commerce, and regional connectivity

 

Summary:

The First Amendment to the LAP Agreement amends the original Project Description in Exhibit A of the LAP Agreement by reducing the project length.  The Project Description has been revised to design of a five (5) foot wide sidewalk on the south side of 62nd Avenue N from 62nd Street N to east of 58th Street N.  This reduction in project length was revised from the original project limits from 62nd Street N to 55th Street N.  The County completed the segment of sidewalk between 55th Street N and east of 58th Street N as part of a prior County project.  The County is also providing intersection improvements on 62nd Avenue N and 58th Street N as part of this sidewalk improvement project and will be responsible for the design and construction costs associated with the intersection portion of the project.

The agreement provides 100% of the funding needed for design activities associated with the 62nd Avenue Sidewalk Improvement Project from 62nd Street N to east of 58th Street N.  Design costs are $133,290.00 for the sidewalk improvements.  It is also anticipated that FDOT will provide 100% of the construction costs associated with this design work as well.  Design activities are underway with final design scheduled for February 9, 2019.

 

Background/Explanation:

The purpose of the grant funded portion of this project is for design and construction of a five foot sidewalk on the south side of 62nd Avenue N from 62nd Street N to east 58th Street N.  The addition of new pedestrian signal heads, sidewalk connectors and crosswalks to facilitate the crossings at 62nd Street N and 58th Street N are also included as part of the intersection improvement portion of the project.  The project length is approximately 0.629 miles. 

 

Fiscal Impact:

N/A

 

Delegated Authority:

Authority for the County Administrator to sign this amendment is granted under Code Section 2-62 (a)(2).

 

Staff Member Responsible:

Addie Javad, Director, Public Works

 

Partners:

FDOT

 

Attachments:

First Amendment
Project Location Map