File #: 17-1186A    Version: 1
Type: Contract/Agreement Status: Passed
File created: 6/30/2017 Department: Real Estate Management
On agenda: 9/26/2017 Final action: 9/26/2017
Title: Award of bid to Anderson & Shah Roofing, Inc. of Florida for the roof recoating project at the Young-Rainey STAR Center.
Attachments: 1. Bid tabulation, 2. Location Map
Related files: 17-2210A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Award of bid to Anderson & Shah Roofing, Inc. of Florida for the roof recoating project at the Young-Rainey STAR Center.

label

 

Recommended Action:

Recommended Action

Approve the award of bid to Anderson & Shah Roofing, Inc. of Florida for the Roof Recoating Project at the Young-Rainey STAR Center (STAR Center) (Phase 3 - Area 9).

Bid no. 167-0453- B(PF); PID no. 002885A; in the amount of $271,000.00 on the basis of being the lowest responsive, responsible bid received meeting specifications. 

Body

 

Strategic Plan:

Practice Superior Environmental Stewardship
3.4 Reduce / reuse / recycle resources including energy, water, and solid waste

Foster Continual Economic Growth and Vitality
4.1 Proactively attract and retain business with targeted jobs to the County and the region
4.4 Invest in infrastructure to meet current and future needs

Deliver First Class Service to the Public and Our Customers
5.2 be responsible stewards to the public’s resources
5.4 Strive to exceed customer’s expectations

 

Summary:

The purpose of this project is to recoat a portion of the roofing system at the STAR Center (Phase 3 - Area 9).  The recoating in this area will eliminate leaks and prolong the life of the underlying roof system.  Estimated completion of the project is 70 consecutive calendar days.

 

Background Information:

This project involves the recoating of the subject roof area with a waterproofing product, and any ancillary repairs.  The area in question is mainly above anchor tenant’s electronic equipment production assembly lines.

The award recommendation is for the base bid amount only.  The invitation to bid included an alternate for additional square footage; the alternate is not recommended for award as it is beyond the project budget.

Currently, there is a contract for sale of the STAR Center, but contingent upon the resolution of several survey and title issues.  There is no guarantee the sale will take place.  The project is needed to eliminate several leaks in this roof section above the anchor tenant’s manufacturing footprint.  If leaks continue, there is a potential liability risk for intruding water to damage the tenant area and/or create an indoor air quality issue.

 

Fiscal Impact:

Total expenditure not to exceed:     $271,000.00

 

Funding is derived from the STAR Center Capital Improvement Fund.

 

Staff Member Responsible:

Andrew W. Pupke, Director, Real Estate Management
Joe Lauro, Director, Purchasing

 

Partners:

N/A

 

Attachments:

Bid Tabulation
Location Map