ROLL CALL
1.
Utility Work by Highway Contractor Agreement and Three-Party Escrow
Agreement with the Florida Department of Transportation for the State
Road 55/U.S. Highway 19 project from State Road 580 to Northside
Drive.
Approval of the Utility Work by Highway Contractor Agreement and Three-Party Escrow
Agreement with the Florida Department of Transportation (FDOT) for the State Road
55/U.S. Highway 19 project from State Road 580 to Northside Drive.
Recommendation:
* Agreement includes work for relocation of underground water transmission and water
distribution infrastructure to accommodate roadway and drainage improvements by
FDOT within its right-of-way. Work also includes removal of one 36" water valve,
replacement of three 36" water valves, and one 42" water valve.
* Anticipated maximum total project cost for utility work, contingencies, construction
engineering inspection and staff time is $10,177,944.00.
* An amount of $8,889,040.00 will be placed in escrow no later than fourteen days prior
to FDOT bid advertisement for the anticipated total cost of construction.
* Funding for this project is derived from the Water Renewal and Replacement Fund,
over two fiscal years, including FY 2023, as detailed in the Fiscal Impact section of this
report.
* The planned date for FDOT's contractor to begin construction work is September
2022.
* The agreement is effective upon full execution and will remain in effect until project
completion,
County PID No. 001522A and FDOT Financial Project ID No. 256774-2-52-01 for an
amount not to exceed $9,777,944.00; Authorize the Chairman to sign and the Clerk of
the Circuit Court to attest.
2.
Utility Work by Highway Contractor Agreement and Three-Party Escrow
Agreement with the Florida Department of Transportation for the State
Road 55/U.S. 19 project, from Northside Drive to County Road 95.
Approval of the Utility Work by Highway Contractor Agreement and Three-Party Escrow
Agreement with the Florida Department of Transportation (FDOT) for the State Road
55/U.S. 19 project, from Northside Drive to County Road 95.
Recommendation:
* Agreement includes work for relocation of underground water transmission and
distribution infrastructure to accommodate roadway and drainage improvements by
FDOT within their US 19 right-of-way.
* County's anticipated total project cost for utility work is $6,432,525.00 with a
not-to-exceed amount of $7,075,777.50, including contingencies.
* An escrow agreement is established for payment by FDOT to the contractor for the
County's utility relocation work, separate from their construction contract. An amount of
$6,432,525.00 will be placed in escrow by the County no later than fourteen (14) days
prior to FDOT bid advertisement for the anticipated total cost of construction.
* The County is seeking approval for FDOT's contractor to complete the utility work
while performing the state project based on cost and efficiency savings.
* Planned date for FDOT's contractor to begin construction is September 2022.
* These agreements are effective upon full execution and will remain in effect until
project completion.
County PID No. 001523A and FDOT Financial Project ID No. 256774-3-56-02 for an
amount not-to-exceed $7,075,777.50; Authorize the Chairman to sign and the Clerk of
the Circuit Court to attest.