Award of bid to TLC Diversified, Inc. for sanitary sewer pump station repair, rehabilitation and improvement projects for FY 2018-2021.
label
Recommended Action:
Recommended Action
Approval of award of bid to TLC Diversified, Inc. for sanitary sewer pump station repair, rehabilitation and improvement projects for Fiscal Year 2018 - 2021.
Bid No. 178-0360-CP(JJ); PID No. 000964A; in the amount of $5,722,777.00 on the basis of being the lowest responsive, responsible bid received meeting specifications. All work is expected to be completed within 1,095 consecutive calendar days. Authorize the Chairman to sign and the Clerk of Court to attest.
Body
Strategic Plan:
Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs
Deliver First Class Services to the Public and Our Customers
5.3 Ensure effective and efficient delivery of county services and support
Summary:
This contract will provide for repair, rehabilitation and improvements to sanitary sewer pump stations at various locations throughout the County. Pump station repair and rehabilitation is essential for the prevention of sanitary sewer spills. Some of the County stations are now over thirty (30) years old. As equipment becomes obsolete, it is necessary to upgrade to newer technology and communication options in order to repair deteriorated pumps and piping. These improvements are facilitated in order to keep the sanitary sewer collection system functioning at an acceptable level.
Background Information:
Work may include furnishing and installation of pumps, valves, fittings, electrical equipment, panels, conduits, vaults, trenching/boring, bypass pumping, dewatering, restoration, testing and other incidental work required to re-commission a pump station.
Award of this contract is consistent with the sanitary sewer pump renewal and replacement program based on a twenty (20) year life cycle and is consistent with the recommendations of the Stormwater/Wastewater Taskforce.
Fiscal Impact:
Expenditure not to exceed: $5,722,777.00.
Project funding is derived from the capital improvement program, physical environment, sewer renewal & replacement program allocation and from the Utilities Department sanitary sewer enterprise fund.
Staff Member Responsible:
Megan Ross, Interim Director, Utilities
Joe Lauro, Director, Purchasing
Partners:
N/A
Attachments:
Agreement