Title: Time only extension to the Local Agency Program Agreement with the Florida Department of Transportation for the Keystone Road shoulder and resurfacing project.
Attachments: 1. Time Extension.pdf, 2. Project Location Map
Related files: 17-122A, 18-1147D
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Time only extension to the Local Agency Program Agreement with the Florida Department of Transportation for the Keystone Road shoulder and resurfacing project.

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of the time only extension to the Local Agency Program (LAP) Agreement with the Florida Department of Transportation (FDOT) for the Keystone Road shoulder and resurfacing project.

FDOT financial project no. 436011 1 58 01, County PID no. 001769A.

Body

 

Strategic Plan:

Ensure Public Health, Safety, and Welfare
2.5 Enhance pedestrian and bicycle safety
Foster Continual Economic Growth and Vitality

4.4 Invest in infrastructure to meet current and future needs
4.5 Provide safe and effective transportation systems to support the efficient flow of motorists, commerce, and regional connectivity

 

Summary:

The County requested and FDOT granted a six (6) month time only extension to the subject LAP agreement due to delays caused by unsuitable subsurface material causing a pipe structure to not be properly supported.  Additional geotechnical investigation is required for an alternative resolution process. 

The FDOT granted a six (6) month time extension to prolong the duration of the LAP agreement from August 15, 2018 to February 15, 2019.

 

Background/Explanation:

The Board of County Commissioners approved this grant on March 7, 2017 to partially fund the Keystone Road shoulder and resurfacing project.  Construction activities commenced on August 7, 2017.  The project is substantially complete with the exception of additional geotechnical investigation work that is necessary for an alternative resolution process.

 

Fiscal Impact:

N/A

 

Delegated Authority:

Authority for the County Administrator to sign this time extension is granted under Code Section 2-62 (a)(2).

 

 

Staff Member Responsible:

Rahim Harji, Assistant County Administrator

 