Preliminary Engineering Agreement with CSX Transportation for the Forest Lakes Boulevard Phase III Widening Project.
label
Recommended Action:
Recommended Action
Approval and execution by the County Administrator of the Preliminary Engineering Agreement (Agreement) with CSX Transportation (CSXT) for the Forest Lakes Boulevard Phase III Widening Project.
• Forest Lakes Boulevard is in the design phase for widening from the existing two-lane roadway to a five-lane typical section. The proposed road widening requires the widening and replacement of the existing CSXT rail crossing just north of SR580.
• CSXT will be responsible for review of engineering plans for reconstruction of existing railroad crossing.
• CSXT will develop cost estimates for the railroad components of the project.
• Total anticipated cost of Agreement to County is $48,500.00, of which $2,500 has already been paid to CSXT to initiate this project. Balance to be paid to CSXT is $46,000.00. Should CSXT exceed this estimate, CSXT will provide County with a revised estimate.
• Funding is budgeted under the Forest Lakes Blvd Phase III - From Tampa Rd. to SR 580 Project 003914A, included in the Capital Improvement Plan, funded by the Penny for Pinellas, Multimodal Impact Fees (MMIF), and state grant funding.
PID No. 003914A; CSXT OP No. FL3164; Total cost to County is $46,000.00.
Body
Strategic Plan:
Ensure Public Health, Safety and Welfare
2.1 Provide planning, coordination, prevention, and protective services to ensure a safe and secure community.
Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs.
4.5 Provide safe and effective transportation systems to support the efficient flow of motorists, commerce, and regional connectivity.
Deliver First Class Services to the Public and Our Customers
5.3 Ensure effective and efficient delivery of County services and support.
Summary:
The purpose of this Agreement is for CSXT to provide review of engineering services for the reconstruction of the rail crossing at Forest Lakes Boulevard (CR 233). Services include the review of various engineering documents as well as attendance by CSXT representatives at project meetings.
The Project will widen and replace an existing rubber crossing surface with a concrete tub-platform and new railroad signals at Forest Lakes Boulevard (CR 233). CSXT will be responsible for the review and preparation of the design and engineering plans for the reconstruction of the existing railroad crossing. CSXT will develop construction cost estimates for the railroad components of the project.
Background/Explanation:
The current crossing consists of rubber panels that will be widen and replaced with a concrete tub crossing and railroad signals. Since the crossing is part of CSXT right-of-way (ROW), CSXT will be involved in the design and review of documents relating to the reconstruction of the crossing.
Fiscal Impact:
Funding is budgeted under the Forest Lakes Blvd Phase III - From Tampa Rd. to SR 580 Project 003914A, included in the Capital Improvement Plan, funded by the Penny for Pinellas, Multimodal Impact Fees (MMIF), and state grant funding.
Delegated Authority:
Authority for the County Administrator to sign this Agreement is granted under Code Section 2-62 (a)(1).
Staff Member Responsible:
Kelli Hammer Levy, Director, Public Works
Partners:
CSXT
Attachments:
Agreement
Project Location Map