On agenda: 3/31/2025 Final action: 1/3/2025
Title: Change Order 1 (final) to Air Mechanical & Service Corp., for 23-1128-ITB-C Star Center Chiller 2 Replacement.
Attachments: 1. CO1 23-1128 signed, 2. OMB.REVIEW_24-1271D_FinalCO_Star_Center_Chiller#2_AirMech&ServiceCorp.pdf, 3. OMB.REVIEW_24-1271D_Project_004082A_Budget_Detail_Report.pdf
Related files: 23-1636A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Change Order 1 (final) to Air Mechanical & Service Corp., for 23-1128-ITB-C Star Center Chiller 2 Replacement.

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of Change Order No.1 (final) to the agreement with Air Mechanical & Service Corp., for 23-1128-ITB-C Star Center Chiller 2 Replacement.

 

                     The original item was approved by the Board of County Commissioners (BCC) on December 12, 2023, for the installation of a new energy efficient 900-ton water-cooled chiller #2 to replace a failed chiller in the central plant located in building 500 at the STAR Center.

                     This item is for the final change order to the original agreement. The change order will decrease the original agreement amount of $977,540.00 by ($48,549.00) for a revised Agreement total of $928,991.00.

                     This decrease comes as a result of unused project contingency.

                     This reduction did not increase or reduce the overall project schedule.

                     Funding is budgeted under the STAR Center Chiller #2 Replacement Project 004082A included in the Capital Improvement Plan funded by the STAR Center Fund.

 

Contract No. 23-1128-ITB-C decreasing the Agreement by ($48,549.00) for a revised Agreement total of $928,991.00.

Body

Strategic Plan:

Practice Superior Environmental Stewardship
3.4 Reduce / reuse / recycle resources including energy, water, and solid waste
Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs
Deliver Fist-Class Services to the Public and Our Customers
5.3 Ensure effective and efficient delivery of county services and support.

 

Summary:

It was determined during construction only a partial amount of contingency had to be utilized. This resulted in a reduction to the total project amount contract price. This reduction did not increase or reduce the overall project schedule.

 

Background/Explanation:

Provided and installed turnkey a new energy efficient 900-ton water-cooled chiller #2 to replace a failed chiller in the central plant located in building 500 at the STAR Center.

 

Fiscal Impact:

Funding is budgeted under the STAR Center Chiller #2 Replacement Project 004082A included in the Capital Improvement Plan funded by the STAR Center Fund.

 

Delegated Authority:

Authority for the County Administrator to execute this Change Order No.1 final is granted under Code Section 2-62(a)(3).

 

Staff Member Responsible:

Cynthia Johnson, Director, Economic Development
Merry Celeste, Purchasing & Director, Administrative Services
Joe Lauro, Director, Administrative Services

 

Partners:

N/A

 

Attachments:

Change Order 1 (final)