File #: 19-601A    Version: 1
Type: Contract/Agreement Status: Regular Agenda
File created: 4/15/2019 Department: Airport
On agenda: 9/12/2019 Final action: 9/12/2019
Title: Award of bid to Ajax Paving Industries of Florida, LLC for the St. Pete-Clearwater International Airport Runway 18-36 Rehabilitation project. (Companion to Item No.14)
Attachments: 1. Agreement, 2. Bid Tabulation, 3. Project Financial Overview, 4. Location Map - Runway 18-36 Rehabilitation
Related files: 19-1094A, 19-1704A, 19-1637A, 19-1638A

Subject:

Title

Award of bid to Ajax Paving Industries of Florida, LLC for the St. Pete-Clearwater International Airport Runway 18-36 Rehabilitation project. (Companion to Item No.14)

label

 

Recommended Action:

Recommended Action

Approval of the award of bid to Ajax Paving Industries of Florida, LLC for the St. Pete-Clearwater International Airport (Airport) Runway 18-36 Rehabilitation project.

 

                     This project consists of design and construction of Airport Runway 18-36 and Runway 4 extension.

                     Two bids were received with award recommendation to the lowest, responsive responsible bidder, Ajax Paving Industries of Florida, LLC, (Ajax) in the amount of $22,565,120.10.

                     All work is expected to be completed within 448 consecutive calendar days.

                     Ajax will subcontract over $1,000,000.00 to Small Business Enterprise qualified firms.

 

Bid No. 189-0334-CP (LN); PID No. 000035A in the amount of $22,565,120.10 on the basis of being the lowest responsive, responsible bid received meeting specifications.  Authorize the Chairman to sign and the Clerk of the Court to attest.

Body

 

Strategic Plan:

Foster Continual Economic Growth and Vitality
4.4 Invest in Infrastructure to meet current and future needs

 

Summary:

This project consists of the construction of the Airport Runway 18-36 and Runway 4 extension.  This project includes asphalt pavement milling; pavement reconstruction; grading and drainage; subbase and base installation; pavement marking; airfield electrical; and procurement and installation of runway/taxiway closure devices.  As part of this project, the secondary runway, Runway 4-22, will be extended by 100 feet to accommodate air carrier traffic while Runway 18-36 is being rehabilitated.  Work is expected to be completed within 448 consecutive calendar days.

 

Background Information:

The Airports primary runway, Runway 18-36, is in need of rehabilitation due to pavement distresses; such as, longitudinal cracking, raveling, and weathering. The Airport has performed several emergency repairs over the past several years to maintain operational service of this primary runway, but a comprehensive pavement rehabilitation is needed. This project will repair and reconstruct the primary runway, as well as, provide a new widened asphalt shoulder and includes a complete replacement of all in-pavement edge lights.

 

Fiscal Impact:

Total expenditure not to exceed:  $22,565,120.10

 

Runway 18 - 36 Rehabilitation (PID #000035A)

 

FAA:                         $19,228,608.00*
FDOT:                      $     900,000.00
AIRPORT FUND:    
$ 2,436,512.10**

TOTAL                     $22,565,120.10

 

*The FAA share includes FY2019 PIE entitlements of $4,161,816.00, estimated FY2020 PIE entitlements of $3,482,264.00, and FY2019 discretionary of $11,584,528.00.  The FAA grant application is contained in Granicus #19-1094A.

 

**The Airport Fund’s share includes the local share of FAA grant funded elements ($1,236,512.10) and an FAA unfunded item of Owner’s Contingency of $1.2M.

 

Project funding is derived by the funding described above, along with a $900,000.00 Florida Department of Transportation Public Transportation Grant Agreement approved by the Board of County Commissioners on November 20, 2018.

 

 

Staff Member Responsible:

Thomas Jewsbury, Director, St. Pete-Clearwater International Airport
Joe Lauro, Director, Purchasing

 