Title: Award of bid to Preferred Materials, Inc. for Fiscal Year 2027 Pavement Preservation - Package 2.
Attachments: 1. Agreement-26-0362 FY27 Pavement Preservation Pkg 2 - SIGNED, 2. Tabulation 0362, 3. LOCATION MAP FY27 PACKAGE 2 CONTRACT # 26-0362, 4. OMB.REVIEW_26-1471A_Projects_004192A&005700A_Budget_Detail_Report.pdf, 5. OMB.REVIEW_26-1471A_PavPres_PreferredMaterials_27.pdf, 6. OMB.REVIEW_26-1471A_004192A&005700A_Tracking_Spreadsheet.pdf

Subject:

Title

Award of bid to Preferred Materials, Inc. for Fiscal Year 2027 Pavement Preservation - Package 2.

label

 

Recommended Action:

Recommended Action

Approval of the award of the bid to Preferred Materials, Inc. for Fiscal Year (FY) 2027 Pavement Preservation - Package 2.

 

•                     The proposed FY27 Pavement Preservation Package 2 contract consists of milling and resurfacing, pavement marking, detector loops, and traffic control required to complete the following four projects:

o                     Project A-PID 006831A- McMullen Booth Road - Curlew to SR 580 Resurfacing (Clearwater)

o                     Project B-PID 006772A - Local group Lansbrook B Resurfacing (Palm Harbor)

o                     Project C-PID 006825A - Local Group 212 Resurfacing (Clearwater)

o                     Project D-PID 006826A- Local Group 221 Resurfacing (Largo)

•                     Four bids were received with an award recommendation to Preferred Materials, Inc. in the amount of $4,973,836.00, 24.23% below the Engineer’s Estimate.

•                     The Small Business Enterprise commitment is 7% for this contract.

•                     All work will be completed within 210 consecutive calendar days.

•                     Funding for this agreement, is included in the Capital Improvement Plan, budgeted under the Road Resurfacing & Rehabilitation PIV Project 004192A funded by the Penny for Pinellas and the Transportation Millage Capital Resurfacing Program Project 005700A funded by the Transportation Millage.

 

Contract No. 26-0362-ITB-C, for $4,973,836.00, with all work to be completed within 210 consecutive calendar days; Authorize the Chairman to sign and the Clerk of the Circuit Court to attest.

Body

 

Strategic Priorities:

Resilient Infrastructure and Environment
1.1 Improve traffic flow efficiency.
1.2 Maintain and enhance County infrastructure.

 

Summary:

Summary

The proposed FY2027 Pavement Preservation Package 2 contract consists of milling and resurfacing, pavement marking, detector loops and traffic control devices required to complete the following four (4) projects:
Project A-PID 006831A- McMullen Booth Road - Curlew to SR 580 Resurfacing (Clearwater)
Project B-PID 006772A - Local group Lansbrook B Resurfacing (Palm Harbor)
Project C-PID 006825A - Local Group 212 Resurfacing (Clearwater)
Project D-PID 006826A- Local Group 221 Resurfacing (Largo)

Body

 

Background Information:

On July 21, 2026, the Purchasing Division, on behalf of the Public Works Department, advertised an invitation to bid. Four (4) bids were received, with an award recommendation to Preferred Materials for $4,973,836.00 as the lowest responsive and responsible bidder.  This bid was opened on August 20, 2026, and the department recommendation to award the contract was received on August 28, 2026.

As part of our Annual Pavement Preservation Program multi-year work order contracts have regularly been used to complete large amount of milling and resurfacing projects required to ensure an acceptable level of service for the residents of Pinellas County. However, this contract is a design-bid-build contract for specific projects with a much shorter duration to help ensure the four included projects are completed in a timely
fashion as part of the FY 2027 paving program. These projects were identified primarily by their low Pavement Condition Index (PCI) numbers which is the metric used to determine the annual pavement preservation program. Successful completion of these projects will help increase the average countywide PCI number and improve pavement quality within these communities.

 

Fiscal Impact:

Funding for this agreement, is included in the Capital Improvement Plan, budgeted under the Road Resurfacing & Rehabilitation PIV Project 004192A funded by the Penny for Pinellas and the Transportation Millage Capital Resurfacing Program Project 005700A funded by the Transportation Millage.

 

In the event that future fiscal year funding is not available for this project, the County maintains the authority to terminate this agreement.​

 

Staff Member Responsible:

Kelli Hammer Levy, Director, Public Works
Merry Celeste, Purchasing Division Director, Office of Management & Budget
Chris Rose, Director, Office of Management & Budget

 

Partners: