File #: 22-0789D    Version: 1
Type: Purchasing Delegated Item Status: Passed
File created: 7/20/2022 Department: Economic Development
On agenda: 9/30/2022 Final action: 10/25/2022
Title: Change Order No. 1 with Gibson Air Conditioning and Refrigeration, LLC for the STAR Center Air Handler Replacement project 138, 154, and 189.
Attachments: 1. Staff Report BCC 5-10-22, 2. 004564A_BudgetDetail
Related files: 24-0156D
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Change Order No. 1 with Gibson Air Conditioning and Refrigeration, LLC for the STAR Center Air Handler Replacement project 138, 154, and 189.

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of Change Order No. 1 with Gibson Air Conditioning and Refrigeration, LLC for the STAR Center Air Handler Replacement project 138, 154, and 189.

 

                     This project consists of supplying, installing, and replacing three current air handler units at the STAR Center which are beyond their useful life.

                     Change Order No. 1 increases the contract by $13,653.00 due to price increases resulting from market conditions as a result of supply chain constraints for a new total of $888,653.00 and extends the agreement term by 230 consecutive calendar days for a new total duration of 480 consecutive calendar days.

                     The Board of County Commissioners awarded this project on May 10, 2022.

                     Funding is derived from the STAR Center CIP Fund.

 

Contract No. 22-0090-CP-MJ Change Order No. 1 increase in the amount of $13,653.00 for a new total of $888,653.00 and extending the agreement term by 230 consecutive calendar days for a new total duration of 480 consecutive calendar days.                      Body

Strategic Plan:

Practice Superior Environmental Stewardship
3.4 Reduce / reuse / recycle resources including energy, water, and solid waste

Foster Continual Economic Growth and Vitality
4.1 Proactively attract and retain business with targeted jobs to the County and the region
4.4 Invest in infrastructure to meet current and future needs

 

Summary:

Due to supply chain issues, we are granting the contractor, (Gibson Air Conditioning & Refrigeration LLC), a time-extension and increase to their agreement. The Agreement term has been increased by 230 consecutive Calendar Days for new Agreement Term of 480 consecutive Calendar Days and the agreement amount increased by $13,653.00 for a Revised Agreement Amount of $888,653.00.

 

Background/Explanation:

Three AHUs in STAR Center’s main building 100 have reached their useful life expectancy.  Replacement of these AHUs with new energy efficient units and updated energy management controls will allow the County to provide the air conditioning and heating required for the comfort of its tenants in the areas served by those unit.

 

Fiscal Impact:

Original Agreement Amount:                                           $875,000.00

Increase due to Change Order No. 1:                      $  13,653.00

                     Revised Agreement Amount:                                           $888,653.00

 

Funding for this project is derived from the STAR Center Fund in the Capital Improvement Program: Economic Environment Function, Industry Development Program, Project 004564A STAR Center AHU 138,154,189 Replacement.

 

Delegated Authority:

Authority for the County Administrator to approve and execute this change order is granted under Code Section 2-62(a)(2).

  

Staff Member Responsible:

Cynthia Johnson, Director, Economic Development
Merry Celeste, Division Director, Purchasing & Risk, Administrative Services
Joe Lauro, Director, Administrative Services

 

Partners:

N/A

 