Pinellas County Logo
File #: 23-1845A    Version: 1
Type: Contract/Agreement Status: Passed
File created: 11/15/2023 Department: Public Works
On agenda: 12/12/2023 Final action: 12/12/2023
Title: Supplemental No. 1 to the State funded Grant Agreement with the Florida Department of Transportation, providing construction and construction engineering inspection for the Advanced Traffic Management System /Intelligent Transportation System project on State Road 586/Causeway Boulevard/Curlew Road from the Honeymoon Park entrance to U.S. 19.
Attachments: 1. FE_448513 1 SR586-Causeway ATMS Supplemental Agreement #1, 2. PE_AATF - Supplemental Agreement No. 1, 3. AATF - Supplemental Agreement No. 1, 4. Agreement-FE, 5. MMOA-FE, 6. RES23-28 -FE, 7. Project Location Map, 8. ATMS North County Phase 2 004541A Budget Detail Report, 9. OMB.REVIEW_23-1843A_23-1845A_SuppGrantFunding004541A North County ATMS PH2
Related files: 23-0257A

Subject:

Title

Supplemental No. 1 to the State funded Grant Agreement with the Florida Department of Transportation, providing construction and construction engineering inspection for the Advanced Traffic Management System /Intelligent Transportation System project on State Road 586/Causeway Boulevard/Curlew Road from the Honeymoon Park entrance to U.S. 19.

label

 

Recommended Action:

Recommended Action

Approval of the Supplemental No. 1 Agreement to the State funded Grant Agreement with the Florida Department of Transportation (FDOT), providing construction and construction engineering inspection for the Advanced Traffic Management System /Intelligent Transportation System project on State Road 586/Causeway Boulevard/Curlew Road from the Honeymoon Park entrance to U.S. 19.

 

                     Original agreement provided $502,000.00 in state funding for the project construction and Construction Engineering Inspection. County match was $1,771,345.00 and total project estimate was $2,273,345.00.

                     Supplemental No. 1 increases state funding by $852,532.00, for a total of $1,354,532.00 and reduces County Match by $416,813.00 to $1,354,532.00.

                     Project estimated current cost is revised from $2,273,345.00 to $2,709,064.00.

                     Supplemental No. 1 also revises Section 6 of the Agreement which includes project cost, and Exhibits "B" Schedule of Financial Assistance and "J" State Financial Assistance (Florida Single Audit Act).

                     Funding is budgeted in the Capital Improvement Plan, in Fiscal Year (FY) 2024 and FY25. The breakdown between funding sources (Local Option Fuel Tax and FDOT grant funding) will be updated during the budget cycle.

 

FDOT FPN 448513 1 54 01; FDOT County Incentive Grant Program funding not to exceed $1,354,532.00; County contribution is $1,354,532.00 and total project estimate is $2,709,064.00; Agreement term expires May 13, 2025; Authorize the Chairman to sign and the Clerk of the Circuit Court to attest.

Body

 

Strategic Plan:

Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs
4.5 Provide safe and effective transportation systems to support the efficient flow of motorists, commerce, and regional connectivity

Deliver First Class Services to the Public and Our Customers
5.2 Be responsible stewards of the public’s resources
5.3 Ensure effective and efficient delivery of county services and support)

 

Summary:

Summary

Due to escalating costs and additional eligible work necessary to connect multiple intersections to fiber on SR 580, the Department is increasing state funding to 50% of the current estimate as allowed per the County Incentive Grant Program (CIGP). Local funds are reduced to the required 50% match.

The CIGP Agreement provides state funding for the construction and CEI funding required for the installation of ATMS/ITS on SR 586/Causeway Blvd/Curlew Rd from Honeymoon Park Entrance to US 19.  Total project estimate is $2,709,064.00. Project scheduled for completion by January 13, 2025.

Project will enhance flow of traffic by providing necessary surveillance of traffic conditions along the roadway, and provide motorists with information for alerts, incidents, and evacuations. Total project length is approximately five point two (5.2) miles. The project consists of new installation of fiber optic cable, CCTV cameras, and dynamic message signs.

Body

 

Background Information:

The Board of County Commissioners (Board) originally approved the Agreement on April 25, 2023. The project is part of an overall implementation of the Countywide ATMS/ITS effort that was adopted and funded by the Board utilizing the Ninth Cent Local Option Fuel Tax (LOFT) in 2006. Due to cost increases and additional work identified on the project, FDOT has agreed to increase the funding from CIGP reducing the amount necessary from the County’s Local Option Fuel Tax.

 

Fiscal Impact:

The County match for the Agreement and subsequent supplemental No. 1 is budgeted in the Capital Improvement Program, under project North County ATMS Phase 2 (004541A) funded by the Local Option Fuel Tax (LOFT).

 

Proposed Funding:

LOFT: $1,354,532.00

CIGP: $1,354,532.00

Total Project Estimate: $2,709,064.00

 

Staff Member Responsible:

Kelli Hammer Levy, Director, Public Works

 

Partners:

FDOT

 

Attachments:

Supplemental Agreement No. 1
Agreement - FE
MMOA -FE
RES23-18 -FE
Project Location Map