File #: 17-909D    Version: 1
Type: Purchasing Delegated Item Status: Passed
File created: 9/20/2017 Department: Public Works
On agenda: 12/31/2017 Final action: 1/23/2018
Title: Change Order No. 1- to the contract with Highway Safety Devices, Inc. for the Advanced Traffic Management System/Intelligent Transportation System Project on Park Boulevard (SR 694) from Gulf Boulevard (SR 699) to Grand Boulevard
Attachments: 1. Change Order No. 1 - Time Only Rev.pdf
Related files: 19-268D
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Change Order No. 1- to the contract with Highway Safety Devices, Inc. for the Advanced Traffic Management System/Intelligent Transportation System Project on Park Boulevard (SR 694) from Gulf Boulevard (SR 699) to Grand Boulevard

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of Change Order No. 1 - time extension to the contract with Highway Safety Devices, Inc. for Advanced Traffic Management System/Intelligent Transportation System Project (ATMS/ITS) Project on Park Boulevard (SR 694) from Gulf Boulevard (SR 699) to Grand Boulevard.

Contract No. 156-0148-CP(DF); PID No. 000175A; extending the Agreement term through December 19, 2017.

Body

 

Strategic Plan:

Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs
4.5 Provide safe and effective transportation systems to support the efficient flow of motorists, commerce, and regional connectivity

Deliver First Class Services to the Public and Our Customers
5.3 Ensure effective and efficient delivery of county services and support

 

Summary:

This change order extends the contract term one hundred fifty (150) consecutive calendar days and is necessary due to design revisions required for closed circuit television camera installations.  The delay in the completion of utility locates impacted the installation of the inter-coastal subaqueous bore.  Additionally, the County made revisions to installation of three (3) video vehicle detection system cameras placed on aluminum poles at three (3) intersections on Park Boulevard due to conflict with existing facilities and utilities within the restricted right-of-way.  The County determined placement of cameras on poles within the medians adjacent to the three (3) intersections was preferable to original plan locations. There is no monetary increase to the contract as a result of this change order.

 

Background/Explanation:

The purpose of the project is to install conduit, fiber optic cable, digital message signs and closed circuit television cameras along Park Boulevard as part of the County ITS network.  The project will enhance traffic flow through video detection and adaptive traffic signal control, provide surveillance of roadway and traffic conditions, and provide motorists information for alerts, incidents and evacuations.

The project is part of an overall implementation of the Countywide ATMS/ITS effort that was adopted and funded by the Board of County Commissioners (Board) utilizing the Ninth Cent Local Option Gas Tax in 2006.  As part of the overall plan, this segment is being constructed based on a priority list of projects developed by the Board and Metropolitan Planning Organization.  The Board approved the subject award on April 26, 2017.

 

Fiscal Impact:

Total expenditure not to exceed: $3,231,688.00

Increase/decrease due to Change Order No. 1: $0.00

Revised expenditure not to exceed: $3,231,688.00

 

Funding is derived from the Ninth Cent Local Option Gas Tax (50%) and grant funding through the Florida Department of Transportation (50%).

 

Delegated Authority:

Authority for the County Administrator to approve and execute this change order is granted under Code Section 2-62 (a)(2).

 

Staff Member Responsible:

Rahim Harji, Director, Public Works
Joe Lauro, Director, Purchasing

 