Pinellas County Florida Banner
File #: 24-1658A    Version: 1
Type: Contract/Agreement Status: Passed
File created: 8/7/2024 Department: Utilities
On agenda: 10/15/2024 Final action: 10/15/2024
Title: Change Order No. 1 to the agreement with Ardurra Group, Inc. for the William E. Dunn Offsite Reclaimed Pump Station Improvements Project to provide full-time construction management and inspection services.
Attachments: 1. FE_AATF Change Order No. 1, 2. AATF Change Order No. 1
Related files: 19-1740A

Subject:

Title

Change Order No. 1 to the agreement with Ardurra Group, Inc. for the William E. Dunn Offsite Reclaimed Pump Station Improvements Project to provide full-time construction management and inspection services.

label

 

Recommended Action:

Recommended Action

Approval of Change Order No. 1 to the agreement with Ardurra Group, Inc. for the William E. Dunn Offsite Reclaimed Pump Station Improvements Project to provide full-time construction management and inspection services.

 

                     This contract was awarded for professional engineering, design development, and future construction administration services for the William E. Dunn Offsite Reclaimed Pump Station Improvements Project.

                     Change Order No. 1 extends the contract for an additional 1,308 days until October 1, 2026, and adds additional scope to the project in the amount of $734,754.04 for full-time construction management and inspection services.

                     This contract was awarded by the Board of County Commissioners on June 2, 2020, in the amount of $752,557.11 for design and bidding services.

                     The construction contract for this project was awarded by the Board of County Commissioners on August 13, 2024, in the amount of $13,898,000.00.

                     Funding for construction administration and inspection services is available under William E. Dunn Offsite Reclaim Pump Station Improvements Project 003747A, included in the Capital Improvement Plan, funded by the Sewer Renewal and Replacement Fund in the amount of $1,542,000.00.

                     Total available funding is the remaining funding in the capital plan after deducting the previously approved construction agreement. Available funding in excess of the recommended not-to-exceed amount for this change order is available for other project costs.

 

Contract No. 190-0031-NC increase in the amount of $734,754.04 for a revised not to exceed expenditure of $1,487,311.15, effective through October 1, 2026; Authorize the Chairman to sign and the Clerk of the Circuit Court to attest.

Body

 

Strategic Plan:

Practice Superior Environmental Stewardship
3.3   Protect and improve the quality of our water, air, and other natural resources

Foster Continual Economic Growth and Vitality
4.4   Invest in infrastructure to meet current and future needs

Deliver First Class Services to the Public and Our Customers
5.2   Be responsible stewards of the public’s resources
5.3   Ensure effective and efficient delivery of county services and support

 

Summary:

Summary

This Change Order provides for the full-time construction management and inspection needed for the improvements to the W.E. Dunn Offsite Reclaim Water Pump Station. The scope of the services will include managing all construction related meetings (attending and moderate); manage the review/approval of all shop drawings, requests for information, and additional work authorizations submitted by the contractor; provide construction observation and inspection for all construction activities; provide daily reports; review all invoices and schedules from the contractor throughout the construction and completion of these improvements.

This construction project is large scale and requires full-time construction services to monitor and manage all activities. The improvements to the Dunn Offsite Pump Station include replacement of four vertical turbine pumps; four automatic strainers, expansion of the existing electrical building; replacement of the electrical switchgear, motor control centers and variable frequency drives; SCADA improvements including a new Local Control Panel with a programmable Logic Controller; a diesel generator system; flow meters, valves and associated piping. Work will also include piping, valving and metering to allow surplus reclaim water to be pumped from the County’s Interconnect PS located in Oldsmar back to the Dunn plant’s reclaim pond. 

Body

 

Background Information:

This contract was awarded by the Board of County Commissioners on June 2, 2020, in the amount of $752,557.11.

The Dunn Offsite Reclaim Water Pump Station was originally constructed in 1987.  In 1998, modifications were made to add four strainers on the discharge side of the pumps.  Components including the vertical turbine pumps, electrical gear and strainers have reached the end of their useful service life. The pump station provides reclaimed water to the north county’s public access reuse system as well as providing critical in-plant water needed to support various treatment processes. The pumps are not able to operate in the preferred operating range and therefore are not able to provide the design flow rates needed. Recently, the pumps have required significant maintenance and have been rebuilt multiple times.

 

Fiscal Impact:

Award not to exceed amount                                           $   752,557.11

Change Order No. 1 increase                                          $   734,754.04

Revised Contract Amount                                                               $1,487,311.15

 

Funding is available under W.E. Dunn WRF Offsite Reclaim Pump Station Improvements Project 003747A, included in the Capital Improvement Plan, funded by the Sewer Renewal and Replacement Fund, and future financing, in the amount of $1,542,000.00.

 

The full project allocation in the Capital Improvement Plan is $15,440,000.00. The Board of County Commissioners approved an agreement with TLC Diversified, Inc. for construction of the W.E. Dunn Offsite Pump Station Improvements in the amount of $13,898,000.00.  The remaining available funding is $1,542,000.00.

 

Staff Member Responsible:

Jeremy Waugh, Director, Utilities
Merry Celeste, Purchasing Director, Administrative Services
Joe Lauro, Director, Administrative Services

 

Partners:

N/A

 

Attachments:

Change Order No. 1