Emergency Construction Change Order No. 3, Contract 24-1061-ITB-C from QRC, Inc., for repair services associated with a 48-inch water main leak repair on SR 580.
label
Recommended Action:
Recommended Action
Approval by the County Administrator of the emergency construction change order with QRC, Inc., for repair services associated with a 48-inch water main leak repair on SR 580.
• Pinellas County Utilities is requesting emergency purchase order to utilize QRC for emergency investigation, isolation, and repair services associated with a leak on the existing 48-inch water transmission main within the westbound lanes of SR 580. Ground-penetrating radar and acoustic sounding equipment identified the leak area adjacent to a 54-inch reinforced concrete pipe, and Pinellas County Utilities initiated traffic control, roadway saw-cutting, and exploratory excavation to locate and expose the source of the leak.
• After excavation, QRC uncovered the damaged area and confirmed significant erosion of the concrete surrounding the 48-inch main. The steel reinforcement has been compromised, and a small hole is present in the steel liner. Because of the size and critical function of the transmission main, the condition requires immediate repair to reduce the risk of a larger failure, roadway damage, and interruption of water service.
• The estimated cost is $1,601,904.96, plus a 10% contingency of $160,190.50, for a total emergency authorization request of $1,762,095.46.
• Per County Code Section 2-181, the County Administrator has authority to approve this emergency repair work.
• Funding for this emergency purchase is not included in the current-year budget. A budget amendment may be proposed following this emergency change order. thority to terminate this agreement...Body
Strategic Plan:
Resilient Infrastructure and Environment
1.2 Maintain and enhance County infrastructure.
Summary:
Approval of an emergency purchase order to QRC, Inc. for repair services associated with a 48-inch water main leak repair on SR 580.
Background/Explanation:
QRC's estimate under the Annual Water and Reclaimed Water Repairs and Extensions contract (Contract No. 24-1061-ITB-C) is $1,601,904.96, plus a 10% contingency of $160,190.50, for a total emergency authorization request of $1,762,095.46. QRC will charge only for actual quantities used in accordance with the estimate. Cityworks work order 2465032 is associated with the incident.
Fiscal Impact:
Contract in the not-to-exceed amount: $1,762,095.46
Funding for this emergency purchase is not included in the current-year budget. A budget amendment will be proposed for approval by the County Administrator following this emergency change order.
Delegated Authority:
Authority for the County Administrator to approve this emergency purchase is granted under Code Section 2-181.
Staff Member Responsible:
Jeremy Waugh, P.E., Director, Utilities
Merry Celeste, Purchasing Division Director, Office of Management & Budget
Chris Rose, Director, Office of Management & Budget
Partners:
N/A
Attachments:
Emergency Memo with contractor estimate