Proposed settlement in the case of Vertex Development, LLC v. Pinellas County, Florida; Federal District Court Case No. 8:22-cv-02012-VMC-CPT.
label
Recommended Action:
Recommended Action
Approve the proposed settlement by authorizing conditional approval to allow construction of the camouflaged communications tower proposed in Case No. TY2-22-11, Board of Adjustment and Appeals with a height limitation of 100 feet.
Body
Strategic Plan:
N/A
Summary:
Summary
The Board of Adjustment and Appeals denied an application for Type-2 Use Approval submitted by Vertex Development, LLC seeking to allow the construction of a 120-foot-tall, camouflaged communication tower and related support facilities on the property of Christ the King Lutheran Church, Inc., located at 11220 Oakhurst Road in unincorporated Largo. A lawsuit was subsequently filed in federal court claiming a violation of the Federal Telecommunications Act for wrongful denial of the requested approval. Cell towers that are camouflaged, such as the one proposed by the Plaintiff, are allowed at the proposed site as a matter of right under the Land Development Code at a height of 75 feet. The Plaintiff has proposed the same camouflaged communication tower and related support facilities, but at a lower height of 100 feet to settle the lawsuit. All other conditions, such as setbacks from neighboring properties, would remain as proposed in the application before the Board of Adjustment and Appeals.
Since Type-2 Use Approvals under the Land Development Code may only be granted after a public hearing, it is recommended that a public hearing be conducted on the proposed settlement. This matter has been advertised as a public hearing as required by the Land Development Code, including mailed notices to nearby residents. Staff is also reaching out to those citizens who appeared at the Board of Adjustment and Appeals hearing.
Body
Background Information:
This matter was previously brought before the Board on October 25, 2022, under Legistar item no. 22-1695A, County Attorney Receipt and File Report.
Fiscal Impact:
Unknown.
Staff Member Responsible:
Jewel White, County Attorney
Christy Donovan Pemberton, Managing Assistant County Attorney
Andrew Keefe, Assistant County Attorney
Carol Stricklin, Department Director, Planning
Partners:
N/A
Attachments:
Board of Adjustment and Appeals staff report for August 3, 2022 meeting
Minutes of Board of Adjustment and Appeals meeting
Board of Adjustment and Appeals denial letter dated August 10, 2022
Summary of Federal Telecommunications Act
TY-22-11-correspondence received
Letters of Opposition received after hearing