Pinellas County Florida Banner
File #: 18-1062D    Version: 1
Type: Purchasing Delegated Item Status: Passed
File created: 11/16/2018 Department: Public Works
On agenda: 4/23/2019 Final action: 4/23/2019
Title: Change Order No. 1 (final) with Florida Safety Contractors, Inc. for the 22nd Avenue South Drainage Improvement project.
Attachments: 1. CO No. 1 (final)
Related files: 17-433A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Change Order No. 1 (final) with Florida Safety Contractors, Inc. for the 22nd Avenue South Drainage Improvement project.

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of Change Order No. 1 (final) with Florida Safety Contractors, Inc. for the 22nd Avenue South Drainage Improvement project at 55th Street South to 51st Street South.

        •
                     Substantial completion achieved on May 10, 2018; final acceptance received on October 1, 2018.
        •
                     Total revised contract duration from commencement of construction to final completion is 412 consecutive calendar days reflective of the 202 calendar day increase due to unforeseen conditions encountered during construction
        •
                     Roadway drainage improvements provide for improved hydraulics, to enable quick draw-down of standing water for both regular and major storm events.
        •
                     These improvements are intended to increase driver safety.

Contract No. 167-0280-CP (JJ); PID No. 002508A; reducing the contract amount by ($231,300.53) for a revised total of $1,451,982.47.

Body

 

Strategic Plan:

Foster Continual Economic Growth and Vitality
4.4 Invest in infrastructure to meet current and future needs
4.5 Provide safe and effective transportation systems to support the efficient flow of motorists, commerce, and regional connectivity

Deliver First Class Services to the Public and Our Customers
5.1 Maximize partner relationships and public outreach

 

Summary:

Change Order No. 1 (final) reduces the Board of County Commissioners (Board) approved expenditure by ($231,300.53) and accepts the contract as complete. The reduction in expenditure is due to the difference between estimated and final quantities, and balance of unspecified work not utilized. Substantial completion for this project was achieved on May 10, 2018; final completion was accepted on October 1, 2018. The protracted time between expected and actual final completion was due to third party utility conflicts, delay associated with contamination cleanup work on private property (responsible party for cleanup was the private property owner) and unforeseen work to complete the project. As part of this change order, the Agreement term is increased by 202 calendar days.

 

Background/Explanation:

This contract was originally awarded by the Board on June 6, 2017 to construct drainage improvements to relieve existing roadway flooding along 22nd Avenue South between 55th Street South to 51st Street South.

 

Fiscal Impact:

Original expenditure not to exceed:                                           $1,683,283.00

Decrease due to change order no. 1 (final):                      $  (231,300.53)

Revised total expenditure:                                                                                      $1,451,982.47

 

Funding for this project is derived from the Infrastructure Sales Tax (Penny for Pinellas): Stormwater Conveyance System Improvement Program, Storm Sewer Rehab Projects allocation.

 

Delegated Authority:

Authority for the County Administrator to approve and execute this change order is granted under Code Section 2-62(a)(3).

 

Staff Member Responsible:

Adnan Javed, Director, Public Works
Joe Lauro, Director, Purchasing

 

Partners:

City of Gulfport

 

Attachments:

Change Order No. 1 (final)