Legislation Details

File #: 25-0908D    Version: 1
Type: Purchasing Delegated Item Status: Passed
File created: 10/8/2025 Department: Construction and Property Management
On agenda: 12/31/2025 Final action: 2/17/2026
Title: Change Order No. 2 (final) to the contract with Manhattan Construction (Florida) Inc., for design-build professional services pertaining to the final closure/completion of the St. Petersburg Justice Center Courts Consolidation project.
Attachments: 1. Change Order No. 2 (final)
Related files: 17-1234A, 19-1237A, 21-1667A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Subject:

Title

Change Order No. 2 (final) to the contract with Manhattan Construction (Florida) Inc., for design-build professional services pertaining to the final closure/completion of the St. Petersburg Justice Center Courts Consolidation project.

label

         

Recommended Action:

Recommended Action

Approval and execution by the County Administrator of the Change Order No. 2 (final) with Manhattan Construction (Florida) Inc., for design-build professional services pertaining to final closure/completion of the St. Petersburg Justice Center Courts Consolidation project.

 

•                     Phase I of the design-build contract was awarded by the Board of County Commissioners (Board) on June 19, 2018, for eight (8) consecutive calendar months in the amount of $633,147.00 for pre-construction services.

•                     The First Amendment Guaranteed Maximum Price (GMP) was approved by the Board on October 8, 2019, in the amount of $11,770,576.00 for 658 consecutive calendar days.

•                     Change Order No. 1 was approved by the Board on September 21, 2021, increasing the contract by $375,000.00 and extending the contract by 237 calendar days.

•                     Change Order No. 2 (final) decreases the contract amount by ($149,233.00) for reconciliation of owner’s contingency and project allowances. In addition, the change order increases the date of substantial completion by 1,176 calendar days for a revised substantial completion date of June 16, 2025.

•                     Funding for this project is budgeted under the St. Pete Courts Consolidation Project 001109C, included in the Capital Improvement Plan, funded by the Penny for Pinellas.

 

Contract No. 167-0496-NC (SS) decrease the contract amount by ($149,233.00) for a revised total amount of $12,629,490.00 and increase the date of substantial completion by 1,176 calendar days for a revised substantial completion date of June 16, 2025.

Body

 

Strategic Priorities:

Resilient Infrastructure and Environment
1.2 Maintain and enhance County infrastructure
Smart Service Delivery
4.2 Achieve and maintain a high level of customer satisfaction.

 

Summary:

Change Order No. 2 (final) decreases the contract amount by ($149,233.00) for reconciliation of owner’s contingency and project allowances. In addition, the change order increases the date of substantial completion by 1,176 calendar days for a revised substantial completion date of June 16, 2025.

 

Background/Explanation:

Phase I of this contract was awarded by the Board on June 19, 2018, for eight (8) consecutive calendar months in the amount of $633,147.00. The First Amendment for GMP was approved by the Board on October 8, 2019, in the amount of $11,770,576.00 for 658 consecutive calendar days. Change Order No. 1 was approved by the Board on September 21, 2021, increasing the contract by $375,000.00 and extending the contract by 237 calendar days.

 

Fiscal Impact:

Original Award - Phase One (pre-construction):                                          $     633,147.00

First Amendment - Phase Two (construction):                                           $11,770,576.00

Change Order No. 1 - Increase:                                                                                     $     375,000.00

Change Order No. 2 (final) - Decrease:                                                                $   (149,233.00)

Final Revised Project Cost:                                                                                     $12,629,490.00

 

Capital funding for this project was budgeted under the St. Pete Courts Consolidation Project 001109C, included in the Capital Improvement Plan, funded by the Penny for Pinellas.

 

Delegated Authority:

Authority for the County Administrator to approve and execute this final change order is granted under Code Section 2-62(a)(3).

 

Staff Member Responsible:

Bill Greer, Director, Construction & Property Management
Merry Celeste, Purchasing Director, Administrative Services
Joe Lauro, Director, Administrative Services

 

Partners:

N/A

 

Attachments:

Change Order No. 2 (final)