Title: First Amendment to the Joint Project Agreement with the City of St. Petersburg for additional utility work associated with the 71st Street North sidewalk, roadway, and drainage improvement project from 38th Avenue North to 54th Avenue North.
Attachments: 1. First Amendment, 2. Exhibit A-First Amendment, 3. JPA with Exhibit A - Executed, 4. Project Location Map, 5. OMB.REVIEW_26-0274A_Amendment#1_JPA_71stSt.pdf, 6. OMB.REVIEW_26-0274A_Projects_000831A&004539A_Budget_Detail_Report - Copy.pdf
Related files: 24-0214A

Subject:

Title

First Amendment to the Joint Project Agreement with the City of St. Petersburg for additional utility work associated with the 71st Street North sidewalk, roadway, and drainage improvement project from 38th Avenue North to 54th Avenue North.

label

 

Recommended Action:

Recommended Action

Approval of the First Amendment to the Joint Project Agreement (JPA) with the City of St. Petersburg (City) for utility work associated with the 71st Street North sidewalk, roadway, and drainage improvement project from 38th Avenue North to 54th Avenue North.

 

                     Original JPA approved by the Board of County Commissioners on July 16, 2024, in the amount of $493,542.00.

                     Bid amount awarded for the City’s work was $683,482.00, with a total amount owed to County by City of $717,656.10 for the original JPA.

                     First Amendment provides increase to JPA in the amount of $214,705.00.

                     There is an outstanding balance of $172,973.57, less applicable accrued interest, owed by City for work under the original JPA.

                     The outstanding balance is added to the additional work amount of $214,705.00 for this amendment for a total owed the County of $388,819.10. After deducting applicable interest of $19,134.76, the total City payable amount is $369,684.34. 

                     Funding for this project is budgeted under the 71st Street North roadway and sidewalk Improvement from 38th Avenue North to 54th Avenue North Project 004539A, funded by the Penny for Pinellas and the American Rescue Plan Act and funded by the Water, Sewer, and Reclaimed Water Relocation Projects Program Project 000831A, funded by the Sewer Renewal and Replacement fund, included in the Capital Improvement Plan.

 

PID 004539A; Amendment is effective upon execution and will expire when construction is complete; Total amount owed by City is $388,819.10, less applicable interest of $19,134.76, for a total of $369,684.34 owed.

Body

 

Strategic Priorities:

Resilient Infrastructure and Environment
1.1 Improve traffic flow efficiency.
1.2 Maintain and enhance County Infrastructure.

Healthy and Safe Communities
2.2 Enhance community safety.

 

Summary:

Summary

The First Amendment to the JPA increases the total amount by $214,705.00. This Amendment to the JPA encompasses the installation of a 2-inch PVC water main, approximately 1,160 linear feet and disposal of the existing antiquated, failing 2-inch galvanized pipe. The existing 2-inch galvanized pipe conflicts with the proposed sidewalk installation due to the insufficient depth and the age of the failing pipe. 

There is an outstanding balance of $172,973.57, less applicable accrued interest, owed by City to County for the original JPA work.    Thus, total amount owed to County is $388,819.10, less applicable accrued interest, and reflected in the Amendment.

Body

 

Background Information:

The County and City entered the original JPA on July 16, 2024. The work consisted of the County’s contractor replacing, relocating or adjusting approximately 434 linear feet of 8-inch ductile iron pipe and approximately 646 linear feet of 6-inch ductile iron pipe in conflict with the proposed drainage construction improvements on 71st Street North, from 38th Avenue North to 54th Avenue North.

 

Fiscal Impact:

There is no fiscal impact to the County’s contribution towards this project for the City’s portion of work under this Amendment to the Joint Project Agreement (JPA). The City’s preliminary estimate for the additional utility work is $186,700.00, plus five percent (5%) or $9,335.00 for contract administration and compaction, and backfill testing costs, and $18,670.00 for unspecified work for an amount of $214,705.00. There is an outstanding balance of $172,973.57 under the original JPA for a total amount of $388,819.10, less applicable interest of $19,134.76, for a total of $369,684.34 to be paid in full by the City.

 

The amended JPA represents the City’s portion of work and is part of a larger County capital improvement planned project. Funding for this project is budgeted under the 71st Street N Roadway and Sidewalk Improvement from 38th Avenue North to 54th Avenue North Project 004539A, funded by the Penny for Pinellas and the American Rescue Plan Act (ARPA), and funded by the Water, Sewer and Reclaimed Water Relocation Projects Program Project 000831A, funded by the Sewer Renewal & Replacement fund, included in the Capital Improvement Plan.

 

Staff Member Responsible:

Kelli Hammer Levy, Director, Public Works

 

Partners:

City of St. Petersburg

 

Attachments:

First Amendment
Exhibit A - Cost Estimate for Amendment
Joint Project Agreement with Exhibit A