Pinellas County Florida Banner
File #: 19-1150D    Version: 1
Type: Purchasing Delegated Item Status: Passed
File created: 11/22/2019 Department: Utilities
On agenda: 1/28/2020 Final action: 1/28/2020
Title: Change Order No.1 to the contract with HORIZON Lab Systems, LLC for software maintenance of a Laboratory Information Management System for the Utilities Water Quality Laboratory.
Related files: 15-1051, 17-1127D, 20-440D
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 Subject:

Title

Change Order No.1 to the contract with HORIZON Lab Systems, LLC for software maintenance of a Laboratory Information Management System for the Utilities Water Quality Laboratory.

label

         

Recommended Action:

Recommended Action

Approval by the County Administrator of Change Order No. 1 to the contract with HORIZON Lab Systems, LLC (HORIZON) for software maintenance of a Laboratory Information Management System (LIMS) for the Utilities Water Quality Laboratory.

 

                     This contract provided for the supply, implementation, and maintenance of a LIMS for the Utilities Water Quality Laboratory.

 

                     Change Order No.1 provides for software maintenance on five (5) additional licenses previously purchased on January 12, 2018.

 

                     Change Order No. 1 increases the annual software maintenance expenditure from $23,298.00 to $23,721.00. ($423.00 per year X 4 years) for a total increase of $1,692.00

 

Contract no. 156-0140-P(JJ); increase in the amount of $1,692.00 (4 year total increase per year is $423.00) for a revised contract amount of $356,112.00.Body

 

Strategic Plan:

Deliver First Class Services to the Public and Our Customers
5.2 Be responsible stewards of the public’s resources.
5.3 Ensure effective and efficient delivery of county services and support
5.4 Strive to exceed customer expectations

 

Summary:

Change Order No. 1 provides for software maintenance on five (5) previously purchased licenses for a period of four (4) years. This will ensure staff is utilizing current, secure, and consistent LIMS reporting system software. The five additional licenses were purchased through Amendment No. 1 on January 12, 2018.

LIMS software licensing purchases and project implementation have been completed. The remaining contract expenditure is annual software maintenance.

 

Background/Explanation:

This contract was originally approved by the Board of County Commissioners on November 22, 2016 for the supply, implementation and maintenance of a LIMS solution for the Utilities Department Water Quality Laboratory. The County Administrator approved Amendment Nos. 1 and 2 on January 12, 2018 and July 1, 2019 respectively.

 

Fiscal Impact:

Current approved expenditure:                                                                $354,420.00

Change Order No. 1 increase                                                                $    1,692.00

Revised contract expenditure not to exceed                      $356,112.00

 

Funding is derived from the Water, Sewer, and Solid Waste Capital fund.

 

Delegated Authority:

Authority for the County Administrator to approve this change order is granted under Code Section 2-62(a)(2)

 

Staff Member Responsible:

Megan Ross, Director, Utilities Department
Merry Celeste, Division Director, Purchasing and Risk Management

 

Partners:

Utilities customers

 

Attachments:

Quote