Pinellas County Florida Banner
File #: 24-1231A    Version: 1
Type: Contract/Agreement Status: Passed
File created: 7/3/2024 Department: Utilities
On agenda: 8/13/2024 Final action: 8/13/2024
Title: Award of bid to Cathcart Construction Company Florida, LLC for the construction of the Manufactured Home Communities Wastewater System Improvements American Rescue Plan Act Project - Package 2 for Lake Seminole Estates, and optional additives of Oasis Homeowners, Inc., and Midway AM/CAN Homeowners, Inc. (Companion to Item No. 21)
Attachments: 1. FE_Agreement-24-0420 (CCC-FLsigned), 2. Agreement-24-0420 (CCC-FLsigned), 3. Award Tabulation, 4. MHCs Map.pdf, 5. OMB.REVIEW_24-1231A_Utilities_MHC2_16-JULY-2024
Related files: 24-1320A

Subject:

Title

Award of bid to Cathcart Construction Company Florida, LLC for the construction of the Manufactured Home Communities Wastewater System Improvements American Rescue Plan Act Project - Package 2 for Lake Seminole Estates, and optional additives of Oasis Homeowners, Inc., and Midway AM/CAN Homeowners, Inc. (Companion to Item No. 21)

label

 

Recommended Action:

Recommended Action

Approval of the award of bid to Cathcart Construction Company Florida, LLC for the construction of the Manufactured Home Communities (MHC) Wastewater System Improvements Project Package 2 American Rescue Plan Act (ARPA).

 

                     MHC Wastewater Collection Systems Improvements Project for the replacement and improvement of 3 wastewater collection systems, erosion control, and site restoration in the Lake Seminole Estates, Oasis Homeowners, and Midway AM/CAN Homeowners Manufactured Home Communities. The proposed improvements ensure the ability to convey wastewater from these MHCs to Pinellas County Utilities treatment facilities during storm events and to meet regulatory requirements. 

                     Award recommendation is to Cathcart Construction Company Florida, LLC, as the lowest responsive and responsible bidder in the amount of $14,793,084.35.

                     All work is to be completed within 698 consecutive calendar days. The Small Business Enterprise commitment is 5% for this contract.

                     Funding is available under Manufactured Home Communities Wastewater Collection Systems Improvements Project 005015A, included in the Capital Improvement Plan, funded by the ARPA Fund, Restore Act federal grant funding, and Resilient Florida Grant program federal grant funds passed through the Florida Department of Environmental Protection, in the amount of $37,994,000.00.

                     The Proposed Fiscal Year 2025-2030 Capital Improvement Plan fully reflects the project’s anticipated cost and is sufficient to fund the recommended contract. In the event that future fiscal year funding is not available for this project, the County maintains the authority to terminate this agreement.

 

Contract No. 24-0420-ITB-C in the amount of $14,793,084.35 with all work to be completed within 698 consecutive calendar days; Authorize the Chairman to sign and the Clerk of the Circuit Court to attest.

Body

 

Strategic Plan:

Ensure Public Health, Safety, and Welfare
2.1   Provide planning, coordination, prevention, and protective services to ensure a safe and secure community
2.2   Be a facilitator, convener, and purchaser of services for those in need

Practice Superior Environmental Stewardship
3.3   Protect and improve the quality of our water, air, and other natural resources
3.5   Foster a sustainable and resilient community that is prepared for sea level rise and a changing climate

Foster Continual Economic Growth and Vitality
4.2   Invest in communities that need the most
4.4   Invest in infrastructure to meet current and future needs

Deliver First Class Services to the Public and Our Customers
5.2   Be responsible stewards of the public’s resources
5.3   Ensure effective and efficient delivery of county services and support

 

Summary:

Summary

This contract is for construction improvements including demolition of existing wastewater systems and construction of a new wastewater system at Lake Seminole Estate.  The optional additive MHCs include Oasis Homeowners, Inc., Midway AM/CAN Homeowners, Inc., with a similar work scope.

Body

 

Background Information:

Various MHCs’ wastewater systems are outdated and problematic. Many assets within these systems fail and pose costly risks to the residents and adverse effects to the environment. Improvements done to the wastewater systems of these flood-prone communities would increase the reliability of service during typical conditions and increase the resilience during wet weather events.

The Purchasing Division issued an invitation to bid on April 23, 2024. Two submittals were received with award recommendation to Cathcart Construction Company Florida, LLC as the lowest responsive and responsible bidder.

 

Fiscal Impact:

Total not to exceed:                                          $14,793,084.35

 

Funding is available under Manufactured Home Communities Wastewater Collection Systems Improvements Project 005015A, included in the Capital Improvement Plan, funded by the American Rescue Plan Act (ARPA) Fund, Restore Act federal grant funding, and Resilient Florida Grant Program federal grant funds passed through the Florida Department of Environmental Protection, in the amount of $37,994,000.

 

Three contracts for completion of Manufactured Home Communities Wastewater Collection Systems Improvements Project 005015A will be recommended for award. The first two contracts, to be recommended to the Board of County Commissioners on August 13, 2024, are fully funded. The Proposed FY25-30 Capital Improvement Plan fully reflects the project’s anticipated cost and is sufficient to fund the recommended contract. In the event that future fiscal year funding is not available for this project, the County maintains the authority to terminate this agreement.

 

ARPA funding must be fully expended by December 31, 2026, and $25,000,000 in Florida Resilient funding must be fully expended by June 30, 2026.

 

Staff Member Responsible:

Jeremy Waugh, Director, Utilities
Merry Celeste, Purchasing Director, Administrative Services
Joe Lauro, Director, Administrative Services

 

Partners:

N/A

 

Attachments:

Agreement

Tabulation

Map