Subject:
Title
Third amendment to the agreement with Temple, Inc., for the purchase of traffic signal products.
label
Recommended Action:
Recommended Action
Approval and signature by the County Administrator of the Third amendment with Temple, Inc., for the purchase of traffic signal products.
• Increased amount is $1,400,000.00 for a new total not to exceed amount of $5,954,964.00; per County Code 2-164(b)(1), the County Administrator is authorized to approve piggyback contracts in any amount from competitively solicited and awarded State of Florida contracts.
• This contract utilizes pricing and scope of work based on the State of Florida Department of Transportation (FDOT) Term Contract No. DOT-ITB-24-9098-SJ but utilizes a county contract for legal provisions.
• Funding for this amendment has been incorporated into the Fiscal Year 2026 Adopted Budget, with costs allocated between the Transportation Trust Fund, Capital Projects Fund, and Emergency Medical Service Fund.
Contract No. 24-0714-S increase of $1,400,000.00 for a revised total not to exceed amount of $5,954,964.00.
Body
Strategic Priorities:
Resilient Infrastructure and Environment
1.1 Improve traffic flow efficiency.
Summary:
Third amendment to the agreement with Temple, Inc for the purchase of traffic signal equipment which requires an increase of $1,400,000.00 for a new total not to exceed amount of $5,954,964.00.
Contract No. 24-0714-S State of FDOT Approved Products Listing (APL) for Traffic Equipment with vendor Temple, Inc is set to expire on June 5, 2026, and the vendor has agreed to extend and honor prices for the next 6 months until a new contract is awarded by FDOT.
Background/Explanation:
This FDOT contract has been in existence since the early 1970’s to provide Approved Products List (APL) for Traffic Equipment. The APL was created to consolidate all products under the FDOT certification requirement into one approved list and consolidate all initial product testing to one statewide test facility.
Fiscal Impact:
Current contract amount: $4,554,964.00
Third Amendment increase: $1,400,000.00
Revised contract amount: $5,954,964.00
Funding for this amendment has been incorporated into the Fiscal Year 2026 Adopted Budget, with costs allocated between the Transportation Trust Fund, Capital Projects Fund, and Emergency Medical Service Fund. Continued funding beyond Fiscal Year 2026 will rely on approval as part of the annual County Operating Budget process.
Delegated Authority:
Authority for the County Administrator to sign this amendment is granted under (Code Section 2-164(b)(1).
Staff Member Responsible:
Kelli Hammer Levy, Director, Public Works Department
Chris Rose, Director, Office of Management and Budget
Merry Celeste, Purchasing Division Director, Office of Management and Budget
Partners:
N/A
Attachments:
Third Amendment