Subject:

Title

Release of Liens for the month of October, November, and December 2025.

label

         

Recommended Action:

Recommended Action

Approval by the County Administrator of the Release of Liens for the month of October, November, and December 2025 for the County Administrator’s Receipt and File Report.

 

Body

 

Strategic Priorities:

Smart Service Delivery
4.2 Achieve and maintain a high level of customer satisfaction
4.4 Pursue continuous improvement

 

Summary:

A Release of Lien, a Bankruptcy Administrative Release or payment of unpaid County Utility fees that have been filed against real property. The Release is filed and recorded by the Clerk of Court.

 

Background/Explanation:

In accordance with County Code, Section 126-2, Utilities file a Release of Lien on real property for unpaid fees for potable water, sanitary sewer and reclaimed water that have been in default for 30 days or more and in the amount of $100.00 or greater.

 

Fiscal Impact:

N/A

 

Delegated Authority:

Authority for the County Administrator to accept these Release of Liens is granted under Code Section 2-62 (a)(8).

 

Staff Member Responsible:

Jeremy Waugh, Director, Utilities

 

Partners:

N/A

 

Attachments:

October 2025 Release of Liens
November 2025 Release of Liens
December 2025 Release of Liens