Subject:
Title
Emergency repair with QRC, Inc. for Hurricane Milton - 74th Avenue North, Seminole-24” & Indian Rocks Road 6” CIP SP3584 and SP3585.
label
Recommended Action:
Recommended Action
Approval by the County Administrator of the emergency repair with QRC Inc. for Hurricane Milton - 74th Avenue North, Seminole-24” & Indian Rocks Road 6” CIP SP3584 and SP3585.
• Emergency purchase order for repairs to 74th Avenue North, Seminole-24” & Indian Rocks Road 6” CIP SP3584 and SP3585, damaged by severe weather conditions brought on by Hurricane Milton.
• 74th Avenue North, Seminole-24” FM has multiple breaks and requires 350LF of 24” ductile iron pipe replaced with PVC pipe. The repairs will require installing line stops, temporary bypass pipes with valves, dewatering, MOT, and road restoration. The cost estimate for this repair is $1,766,366.44.
• Indian Rocks Road 6” WM pipe overhead crossing support structures were damaged; we will replace the line with 440LF of 8” HDPE pipe. The new line will be a subaqueous crossing rather than an overhead exterior crossing. The cost estimate for this repair is $146,009.60.
• Not-to-exceed amount of $1,912,376.00.
• Funds in the amount of $163,726,400.00 are available in the Utilities Department Sewer Revenue and Operating Fund Fiscal Year 2025 Adopted Budget.
Contract No. 25-0173-E in the amount of $1,912,376.00.
,Body
Strategic Plan:
Ensure Public Health, Safety, and Welfare
2.1 Provide planning, coordination, prevention, and protective services to ensure a safe and secure community
Deliver First Class Services to the Public and Our Customers
5.3 Ensure effective and efficient delivery of county services and support
Summary:
Approval of emergency request for Hurricane Milton - two emergency purchase orders for repairs to our water and wastewater infrastructure, which was damaged by severe weather conditions brought on by Hurricane Milton.
The two emergency repairs are as follows:
1. 74th Ave N, Seminole-24” FM has multiple breaks and requires 350LF of 24” ductile iron pipe replaced with PVC pipe. The repairs will require installing line stops, temporary bypass pipes with valves, dewatering, MOT, and road restoration. The cost estimate for this repair is $1,766,366.44.
2. Indian Rocks RD 6” WM pipe overhead crossing support structures were damaged; we will replace the line with 440LF of 8” HDPE pipe. The new line will be a subaqueous crossing rather than an overhead exterior crossing. The cost estimate for this repair is $146,009.60
Background/Explanation:
Utilities emergency request for 74th Ave N, Seminole-24” & Indian Rocks RD 6” CIP SP3584 and SP3585
Fiscal Impact:
Contract in the not-to-exceed amount: $1,912,376.00
The (emergency) Contract not-to-exceed amount of $1,912,376.00 not offset by personnel lapse savings or other savings/reallocations will require a budget amendment.
Delegated Authority:
Authority for the County Administrator to approve this emergency purchase is granted under Code Section 2-181.
Staff Member Responsible:
Jeremy Waugh, PE, Director, Utilities
Merry Celeste, Purchasing Director, Administrative Services
Joe Lauro, Director, Administrative Services